How to generate Relationship Types Report?
The Relationship types report gives project managers an overview of which type of relationship is the most used while creating the project plan and what are the consequences of using different relationships for connecting two or more activities.
According to the DCMA 14 Point Schedule Assessment, at least 90% of all total predecessors’ relationships in the project plan should be Finish-to-Start relationship type.
The look of the Relationship Types report is presented in the image below.
To generate the predefined Activity Metrics Report for your project, select the Reports View, and choose Relationship Types Report from the DCMA 14 group of Reports.
More in Graphical Reports
How to create a DCMA14 Analysis?
How to generate an Activity Metrics Report?
How to generate Constraint Types Report?
How to generate Activity Status Report?
How to generate Activity Reports?
How to generate Project Reports?
How to create Custom Graphical reports?