Rebranding Announcement: PrimaveraReaderTM is now ScheduleReaderTM. Read more

HomeHelp ArticlesProgress UpdateHow to propose new activity with ScheduleReader?

How to propose new activity with ScheduleReaderTM?

You can use this functionality if you want to inform your manager that additional effort is undertaken, that is planned with the ongoing version of project plan.

Several settings must be performed in order the newly activities to be visible in the Gantt Chart:

1. Open theSetting Dialog ButtonSettings dialog from the Progress Update ribbon;

2. In Start UDF and Finish UDF select the fields that will be used for updating process;

Setup Start and Finish UDF's

Note: UDF (User-Defined Fields) are created by the project manager in Primavera P6 and inserted in the .xer file. ScheduleReader users only use the fields for various tasks. You cannot create UDF in ScheduleReader.

Note: User info section is mot obligatory for filling up and its main purpose is to give more detailed information about the updates: who inserted them and when:

- If the Insert Username and Update Date check-box is selected, then when any activity is updated, the Username and the Date & Time will be written in the Excel files that are used for data exchange between ScheduleReader and P6;

- If the Create Excel by Username check-box is selected, then Excel file with the inserted user name will be created and will contain only the updates that particular user inserts. This option is useful when project manager wants to receive separate updates from each person that he/she manages.

Note: After inserting data in User Info section, close the project and restart the application

To insert new activity, perform the following tasks:

1. Select the WBS in which the new activity will be placed.

2. Select the Add Activity feature in the Progress Update ribbon.

3. Insert the Name of the newly inserted activity.

Add new activity

4. Define the Start and Finish dates of the activity.

5. If necessary, insert the activity’s predecessor(s) and successor(s).

Setup predecessors and successor

Once the inserting process is done, the row that contains the new activity will be painted green, while the new bar will be painted pinkPink bar

Example for inserting new activity is presented on the image below.

Example new activity in ScheduleReader

Still have questions?

Our friendly support team is ready to answer your questions and solve your problems via email, phone or demo session.

Email Us Your QuestionRequest Live Demo Session